Jump to the beginning of content

7803CL*

Development of Anderson Road Quarry Site - Construction of Grey Water Treatment Plant

Project Scope

The works mainly comprise construction of Grey Water Treatment Plant for Anderson Road Quarry Site Development.

1. Construction of a grey water treatment plant in the development of Anderson Road Quarry Site with a production capacity of up to 3 300 cubic metres (m3) per day.

Sum Earmarked in Approved Project Estimates for the Contract

$484.3 million

Commencement Date

September 2020

Estimated Completion Date

Fourth Quarter of 2025

Current Progress

Construction is in progress

Project Office in WSD

Consultants Management Division

Consultant

Binnies Hong Kong limited

Contract

Contract No. 4/WSD/19 - Development of Anderson Road Quarry Site - Construction of Grey Water Treatment Plant

Note(*): Entrustment Works under PWP No. 7803CL.