The works mainly comprise construction of Grey Water Treatment Plant for Anderson Road Quarry Site Development.
1. Construction of a grey water treatment plant in the development of Anderson Road Quarry Site with a production capacity of up to 3 300 cubic metres (m3) per day.
$484.3 million
September 2020
Fourth Quarter of 2025
Construction is in progress
Consultants Management Division
Binnies Hong Kong limited
Contract No. 4/WSD/19 - Development of Anderson Road Quarry Site - Construction of Grey Water Treatment Plant
Note(*): Entrustment Works under PWP No. 7803CL.