9045WS
Salt Water Supply for Northwest New Territories – Remaining Works
Project Scope
- construction of a salt water service reservoir (SWSR) with a capacity of 18 100 cubic metres at Tan Kwai Tsuen;
- construction of a salt water pumping station (SWPS) with a pumping capacity of 83 000 cubic metres per day at Lok On Pai;
- uprating of an intermediate booster chlorination plant at Tuen Mun water treatment works (WTW);
- laying of approximately 55.4 kilometres (km) of salt water mains of sizes from 100 millimetres (mm) to 1 000 mm in diameter in Yuen Long – Tuen Mun Corridor areas, Tin Shui Wai and Yuen Long Town; and
- associated greening works.
Approved Project Estimate
$808.4 million
Construction Commencement Date
May 2009
Construction Completion Date
March 2015
Current Progress
Completed
Project Office in WSD
Construction Division
Consultant
Not applicable
Contract
- Contract no. 26/WSD/08 – Salt water Supply for Northwest New Territories - mainlaying along Castle Peak Road between Fu Tei and Tin Shui Wai
- Contract no. 24/WSD/08 – Salt water Supply for Northwest New Territories - Mainlaying in Ping Shan, Hung Shui Kiu and Lam Tei areas
- Contract no. 2/WSD/09 – Construction of Lok On Pai Salt Water Pumping Station and Associated Works
- Contract no. 16/WSD/09 – Salt water Supply for Northwest New Territories - Mainlaying in Yuen Long
- Contract 24/WSD/09 – Salt Water Supply for Northwest New Territories – Construction of Tan Kwai Tsuen Salt Water Service Reservoir and Associated Works
- Contract 11/WSD/09 – Supply and Installation of Mechanical and Electrical Equipment for Salt Water Supply for North West New Territories
- Contract 7/WSD/10 – Supply and Installation of Intermediate Booster Electrochlorination Plant for Salt Water Supply for Northwest New Territories
9045WS