9053WS
Uprating of Chai Wan Salt Water Supply System
Project Scope
- uprating the output capacity of Siu Sai Wan salt water pumping station (SWPS) from 30 000 cubic metres (m3) per day to 41 700 m3 per day;
- laying of about 3.8 kilometres (km) salt water mains ranging from 150 millimetres (mm) to 600 mm in diameter; and
- laying of about 0.3 km fresh water mains of 450 mm in diameter for providing contingent augmentation to salt water supply.
Approved Project Estimate
$379.1 million
Construction Commencement Date
April 2017
Construction Completion Date
May 2021
Current Progress
Completed
Project Office in WSD
Construction Division
Consultant
Not applicable
Contract
Civil Contract
- Contract No. 7/WSD/16 - Uprating of Chai Wan Salt Water Supply System – Mainlaying and Upgrading of Siu Sai Wan Salt Water Pumping Station
(NEC3 ECC Option B)
Mechanical & Electrical Contract
- Contract No. 9/WSD/17 - Uprating of Siu Sai Wan Salt Water Pumping Station