9237WF
Mainlaying along Fanling Highway and near She Shan Tsuen – Stage 2
Project Scope
- Laying of about 2.3 kilometres (km) of fresh water mains of 1 200 millimetres (mm) in diameter along Fanling Highway;
- Laying of about 1.4 km of fresh water mains ranging from 900 mm to 1 400 mm in diameter along Tai Po Road – Tai Wo and near She Shan Tsuen.
Approved Project Estimate
$ 225.5 million
Construction Commencement Date
September 2013
Construction Completion Date
December 2018
Current Progress
Completed
Project Office in WSD
Construction Division
Consultant
Not applicable
Contract
Contract No. 3/WSD/13 – Mainlaying near She Shan Tsuen, Tai Po
9237WF