Project Scope

The scope of the project comprises laying of about 1.4 kilometres of fresh water submarine mains with diameter of 500 millimetres between Lantau and Cheung Chau and the associated land mains at the two landfalls.

Approved Project Estimate

$254.8 million

Construction Commencement Date

October 2013

Construction Completion Date

January 2017

Current Progress

Completed

Project Office in WSD

Construction Division

Consultant

Black & Veatch Hong Kong Limited

Contract

Contract No. 1/WSD/13 - Improvement of fresh water supply to Cheung Chau

Other Related Information

Contractor: China Road - China Pipeline Joint Venture