Jump to the beginning of content

9355WF

Water Supply to New Housing Developments in Sheung Shui and Fanling

Project Scope

  1. construction of a fresh water service reservoir at Tong Hang with a capacity of 55 000 cubic metres (m3);
  2. laying of about 2 kilometres (km) trunk mains with 900 millimetres (mm) diameter connecting to the new service reservoir to existing water supply system;
  3. laying of about 12 km distribution mains with diameters ranging from 150 mm and 700 mm in the south-western part of Sheung Shui and Fanling (SSF) areas and associated service connections;
  4. upgrading of the existing Tai Po fresh water pumping station and laying of associated water mains; and
  5. associated works including environmental mitigation works, landscaping works and other engineering works.

Approved Project Estimate

$1,699.7 million

Construction Commencement Date

September 2018

Estimated Construction Completion Date

Fourth Quarter of 2024

Current Progress

Construction is in progress

Project Office in WSD

Project Management Division

Consultant

Atkins China Limited

Contract