9355WF
Water Supply to New Housing Developments in Sheung Shui and Fanling
Project Scope
- construction of a fresh water service reservoir at Tong Hang with a capacity of 55 000 cubic metres (m3);
- laying of about 2 kilometres (km) trunk mains with 900 millimetres (mm) diameter connecting to the new service reservoir to existing water supply system;
- laying of about 12 km distribution mains with diameters ranging from 150 mm and 700 mm in the south-western part of Sheung Shui and Fanling (SSF) areas and associated service connections;
- upgrading of the existing Tai Po fresh water pumping station and laying of associated water mains; and
- associated works including environmental mitigation works, landscaping works and other engineering works.
Approved Project Estimate
$1,699.7 million
Construction Commencement Date
September 2018
Estimated Construction Completion Date
Fourth Quarter of 2024
Current Progress
Construction is in progress
Project Office in WSD
Project Management Division
Consultant
Atkins China Limited
Contract
9355WF