Project Scope
- construction of Tung Chung No. 2 fresh water service reservoir with a capacity of 40 000 cubic metres; and
- associated geotechnical works, landscaping works and water main connection works.
Approved Project Estimate
$300.2 million
Construction Commencement Date
December 2017
Construction Completion Date
August 2021
Current Progress
Completed
Project Office in WSD
Design Division
Consultant
Not applicable
Contract
Civil Contract
Contract No. 4/WSD/17 - Uprating of Tung Chung Fresh Water Supply System – Construction of Tung Chung No. 2 Fresh Water Service Reservoir
(NEC3 ECC Option A)